a contractor estimates that he can paint a house in 5 days using 6 men. if he actually uses 5 men for the job, how many days will they take to paint the house?

Respuesta :

Einstein08 Einstein08
  • 01-09-2018
it will take 4 days to paint the house with 5 men
Answer Link
tramserran
tramserran tramserran
  • 01-09-2018

1 house = 6 men x 5 days  = 30 man days

Need 30 man days with only 5 men: 30x = 5 men   →  x = 6

It will take 6 days for 5 men to complete the job.

Answer: 6 days


Answer Link

Otras preguntas

The space where fast moving electrons are likely to be found in an atom is called the electron Mass Cloud
I NEED THIS ANSWER NOWWWW PICTURE ATTACHED Which system of inequalities is represented by the graph? y ≤ 3x y > –2x – 1 y > 3x y ≤ –2x – 1 y < –3x y
Choose the system of equations which matches the following graph: A. 5x - y = 7 2x - y = 0 B. 5x - y = 7 2x + y = 0 C. 5x + y = -7 2x + y = 0 D. 5x + y = -7 2x
A man whose weight is 650 N is standing on the ground. The force the ground exerts on him is _____.
Has recent U.S. immigration policy been effective? Why or why not? What do you think should be done on immigration?
horizontal lines should be avoided in photographs t/f
What type of communication is a newsletter. A. Verbal communication b. Nonverbal communication c. Oral communication d. Body language
The united states has _____ court systems.
How did the attack on pearl harbor affect american attitudes toward the japanese?
Question 2 (multiple answer) Which simplifications of the powers of i are correct? There is more than one correct answer. Select all correct answers. i7=i4⋅i3=−