12 workers can do a peice of work in 20 days. How many workers should be added to complete work in 16 days?​

Respuesta :

atchleyamirah69
atchleyamirah69 atchleyamirah69
  • 01-04-2021
3 workers

if 12 workers can do a piece of work in 20 days, then one person can do it in 240 days. 240/16 is 15. That is the number of workers that you need in total to it in 16 days. Since the question ask how many more workers,
15 - 12 = 3 more workers.
Answer Link

Otras preguntas

A chef at a restaurant uses 22 pounds of butter each day. About how many grams of butter does theA chef at a restaurant uses 22 pounds of butter each day. About
An accountant earned $1109 a week last year. What was her yearly salary?
Which statement below is true? a. East Asian nations are members of NAFTA. c. Industry and production is not an important aspect of East Asian economics. b. Eas
Which of the following is true of the planet Earth? The Earth revolves around the Sun. The Earth is the third planet from the Sun. The Earth is the only planet
is this right or wrong( I enjoyed riding the boat)
What causes refraction of light rays? Please help, Thanks.
convert 10 to base 2
Which word signals that a contrast is being made? ing a black pulling Ofish O but something O swirling
what is the y intercept of y=5000(0.98)^x​
Find the magnitude and direction angle of the vector v. v = 15i − 15j