If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, how many containers are required?

Respuesta :

miamonroe56
miamonroe56 miamonroe56
  • 02-06-2017
5 times 100 = 500
500 divided by 20 = 25
25 containers
Answer Link

Otras preguntas

When performing cpr on an infant (lying face-up), you should use:?
How did the story of Moses’ struggles help later generations of the Hebrew people?
A discovery only brings extensive change when
What is 78 with an exponent of 1 million?
What is the expected number of heads that come up when a fair coin is flipped 10 times?
A carpenter needs to cut down piece of wood that is 5.6 feet long to 1.71 feet . What is the measurement of the left over piece ?
Limit x approaches to infinity √x^2+x+1 -√x^2-x-1
In order to solve the problem of minimizing the number of times that a user has to enter a password and the problem of a plaintext transmission of the password
What is the difference between flonase and sensimist?
Deere company holds a​ $10,000 note receivable dated july​ 1, 2015, with​ 10% interest. what adjusting entry is needed on december​ 31, 2015? a. no entry is nee