it takes 20 people 24 days to build a barn. in how many days will the barn be built if they had 32 people working

Respuesta :

bluevortexwitepower bluevortexwitepower
  • 02-02-2019

Answer:

15 days

Step-by-step explanation:

Number of ppl it takes to build a barn in 24 days=20

Time it will take 32 people to build the barn=24*20/32=15 days

Answer Link

Otras preguntas

For a fixed amount of gas at a constant temperature, the volume of the gas is inversely proportional to its pressure. The function IMAGE relates the volume in c
How was the development of the steam engine in response to a fuel shortage?
Kylie was out at a restaurant for dinner when the bill came. She wanted to leave a tip of 32%. What number should she multiply the cost of the meal by to find t
someone help, this is trig, i have to do SOHCAHTOA here, i think this question is for sin but im not sure how to do it
Solve Please Don’t Understand new material teacher is teaching
Which document, delivered to the policy owner, includes information about premium amounts, cash values surrender values, and death benefits for specific policy
what is the value of k2+6 when k=3
Write at least ONE paragraph to describe the Wave experiment.
The table shows your test results for math class. What test score do you need on the last exam to earn 90% of the total points? Test score percent answer needed
2. State the relationship between Agriculture an 1 industries.​