A critical activity is________________.a. an activity that consumes no time but shows precedence between events. b. a milestone accomplishment within the project. c. an activity with zero slack. d/ the beginning of an event.

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 09-03-2020

Answer:

C

Explanation:

Critical activity is the sequential activities from beginning to the end of a project. A lot of projects have a single critical path, although some projects may have more than one critical activity which depends on the flow logic utilized in the project.

Answer Link

Otras preguntas

Ipaliwanag ang slogan "Pagtitipid ay kailangan upang likas na yaman ay mapangalagaan at buhay ay magkaroon ng kaginhawaan"
Athena must have to what to her father A.fight b.obey c.ignore d.comfort
Find the Surface Area of this Prism
Jan has $28 to spend at the carnival. The admission is $6.50, she spends $4.00 on food, and each ride costs $3.00. At most, how many rides can Jan ride?
Which statement about the cells of organisms is accurate? A. plants are unicellular organisms that have specialized function B. all organisms are multicellular
Data were collected on the amount spent by 124 customers for lunch at a major Houston restaurant. Based upon past studies the population variance is known with
Bromine is a red-brown liquid with a density of 3.10 g/mL. A sample of bromine weighing 88.5 g occupies what volume
PLEASE HELP I DONT KNOW HOW TO DO IT PLEASEEEE
Five friends go to a fall festival and they each pay an entry fee of $10. The friends then each spend the same amount of money on lunch at the festival and don’
Which is the most liquid asset? A) jewelry B) change jar C) car D) lake house