A critical activity is________________.a. an activity that consumes no time but shows precedence between events. b. a milestone accomplishment within the project. c. an activity with zero slack. d/ the beginning of an event.

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 09-03-2020

Answer:

C

Explanation:

Critical activity is the sequential activities from beginning to the end of a project. A lot of projects have a single critical path, although some projects may have more than one critical activity which depends on the flow logic utilized in the project.

Answer Link

Otras preguntas

cougar park is shaped like a parallelogram and has an area of 1/16 sqaure mile. Its base is 3/8 mile. What is its height?
Which of the following is a result of gravitational forces in the Solar System? A. the radiation given off by Jupiter B. that Saturn is farther away from
is 127 prime or composite
Dave swam 6 laps and did 9 dives at the swimming pool. Crystal did 4 dives and swam 8 laps. How many more laps than dives did crystal and Dave do
Describe two uses of surfactants
how do you solve twelve less than the quotient of a number and 7 is -2
A concept that helps us to interpret ambiguous sensations is called a:
23. A glass box shaped like a rectangular prism has width 7 inches, length 9 inches, and height 12 inches. It is being shipped in a larger box with width 10 inc
What is a property of a combustion reaction? A. Oxygen gas, O2, is a reactant. B. The products are simpler than the reactants. C. The reactants are simpler than
Simplify the expression 75/153 completely.