If 24 electricians can wire some new houses in 15 days, how many electricians would be required to do the job in 12 days?.

Respuesta :

shishirshrestha989
shishirshrestha989 shishirshrestha989
  • 04-01-2022

Answer:

here,

electrician/days

24 - 15

x(let). -12

direct proportion,

then,

exchange X up 24 down

or,24*15=12*X

or,24*15divided by 12=X

X=30

hence,30 electrician required to do complete in 12 days

Answer Link

Otras preguntas

Find the distance between the points (7,-5) and (2, -5).
I need help with something??? Why is there screams from the next door neighbor?
The ratios are not constant; therefore, the points in the table do not form a direct variation.
A family in which the husband, wife, or both, bring children from previous marriages into a new family is known as a: single-parent family. binuclear family. nu
What did the British trade for in India? Were the French successful in making money?
Find a quadratic model from the news or social media. Describe the model including what the variables represent. If you graphed it, would the parabola open up o
discord is Worthry#4310 paying for a 5 question geometry test
. 2. What is the legal drinking age in the United States? 3. Define fermentation. 4. List 6 ways intoxication can affect a person. 5. Define alcohol poisoning?
Which of the following are not good uses of water resources in the United States? fisheries hydro-electric power desert hotel fountains irrigation
Find the molar mass of AI(NO3)3? Explain plz!