contestada

5. If 15 men can finish a work in 16 days in how many days will 8 men can finish the same work? a. 15 b. 20 c. 30 d. 42​

Respuesta :

davism19 davism19
  • 02-08-2022

Answer:

C. 30

Step-by-step explanation:

15 men do work in 16 days

This means that 7.5 men (15/2) would do that same work in 32 days (16x2).

If the number of men increase, the amount of days decrease.

8 men would do that work in 30 days

8 men > 7.5 men

30 days < 32 days

Answer Link
profereyes12122
profereyes12122 profereyes12122
  • 05-08-2022

Answer:

Option c.

Step-by-step explanation:

It is an inverse proportion, fewer workers more days to finish the job.

15 -----16

8 ----- x

x = (16)(15)/8 = 240/8 = 30 days

Hope this helps

Answer Link

Otras preguntas

What is an adjective phrase?
Which three countries have the least access to technology?
Convert 57 mL to its equivalent in L using dimensional analysis
On a TI-84, how do you stop it from giving you simply a number for an answer when you put in a polynomial divided by another polynomial?
What is 258/300 written as a decimal and a percent???
The cost for n students to attend a workshop is 7n+12 dollars. What is the cost,in dollars for  students to attend?
What features of colonial politics in 18th century America contributed to the development of popular democracy, and what kept political life from being more tru
List five kinds of cases that come under the judicial power of the United States courts.
What number is halfway between 3000 and 4000
On a TI-84, how do you stop it from giving you simply a number for an answer when you put in a polynomial divided by another polynomial?